William Eichler 30 March 2026

Half of approved homes remain unbuilt, council chiefs say

Half of approved homes remain unbuilt, council chiefs say image
Planning permission © LarichD / Shutterstock.com.

New data from the Local Councils Network (LCN) reveals a significant 'build-out' gap, with only 52% of homes granted planning permission since 2012-13 actually being completed.

Despite 62 surveyed councils approving over 633,000 units, only 331,300 have been delivered. Currently, more than 200,000 homes hold valid planning consent but have yet to see construction begin.

The LCN identifies four primary barriers to completion:

Viability: Concerns over profitability and land values.

Market Demand: Fluctuating buyer interest.

Developer Behaviour: Strategic delays by landowners.

Infrastructure Constraints: Lack of essential utilities like water and electricity.

Cllr Richard Wright, chair of the LCN, argued the findings prove the planning system isn't the bottleneck. ‘Councils are approving twice as many homes as are built,’ he stated, calling for a focus on construction delivery rather than just increasing applications.

‘With construction never starting on hundreds of thousands of approved homes, even a modest improvement in build-out rates would make a significant contribution towards meeting national and local housing targets.’

He added: ‘Asking councils to approve even more housing applications, when we already approve about nine in every 10, is missing the point to a complex problem.’

Responding to the LCN's figures, a spokesperson for the Home Builders Federation said: 'Having spent years and significant amounts to get an implementable planning permission, developers would not sit on it and delay their only return on investment without very good reason.

'The majority of these permissions will not yet be at the stage when builders are allowed to start work and will be stuck in the treacle of agreeing final details around planning conditions or highways with understaffed local authority departments.'

Check out: 10 ways councils are responding to new housing and planning policy.

SIGN UP
For your free daily news bulletin
Highways jobs

Programme Manager - Castle Point Borough Council

Essex County Council
Up to £550.0000 per day
Programme Manager - Castle Point Borough Council Castle Point, Essex Full-Time, Temporary 2 month contract £550 per day Umbrella, Outside IR35 Project England, Essex, Thundersley
Recuriter: Essex County Council

Finance Assistant - Debt Collection - 12-month FTC

Essex County Council
Up to £25959 per annum + + 26 Days Leave & Local Gov Pension
Finance Assistant - Debt Collection - 12-month Maternity Cover Fixed Term ContractFixed Term, Full Time£25,081 per annumLocation
Recuriter: Essex County Council

Shared Planning Lawyer

Broxbourne Borough Council
Up to £68,506 pa
Are you a focused, enthusiastic team player who enjoys a varied and interesting caseload Cheshunt, Waltham Cross
Recuriter: Broxbourne Borough Council

Strategic Director of Adult Social Care and Health

Tameside Metropolitan Borough Council
circa £130,000 p.a.
Are you someone who leads with heart, thinks with vision, and delivers with impact? Tameside, Greater Manchester
Recuriter: Tameside Metropolitan Borough Council

Assistant Director of All Age Commissioning

Tameside Metropolitan Borough Council
£107,521 p.a.
Are you someone who leads with heart, thinks with vision, and delivers with impact? Tameside, Greater Manchester
Recuriter: Tameside Metropolitan Borough Council
Linkedin Banner