Chris Hodson 26 April 2021

Proving permeable paving

Proving permeable paving image

Recent trials of various, older concrete block permeable paving projects following long-term use back-up previous research, endorse current minimal maintenance recommendations and debunk misconceptions about clogging up of joints. This research has important implications for the adoption and whole life costs of permeable paving generally. One of the projects involved also reveals major benefits of permeable paving for green infrastructure in the public realm, particularly trees.

Concrete Block Permeable Paving (CBPP) technology has proven itself over successful use around the world since the mid-1980s. Two decades of experience in the UK has demonstrated its long-term performance with minimal, if any, maintenance. But one of the most persistent misconceptions about CBPP technology, impeding its uptake and adoption in some quarters, is that – without maintenance – the joints quickly become clogged with debris and, within a short time, become impermeable preventing water from draining into the paving.

Permeable paving in practice

In fact, over time detritus and silt collects in the upper part of CBPP joint material between blocks, where a surface ‘crust’ (around 5-10mm deep) is formed, protecting the laying course and sub-base material but still allowing infiltration. Also, the performance of CBPP is not significantly affected by moss or weeds in the joints, or by leaves collecting on the surface. Even where localised blockages do occur, in a storm event excess water simply flows to more permeable, adjacent areas.

Previous research has demonstrated that the infiltration rate of CBPP will decrease due to this build-up in the jointing material, but then stabilise with age. Even after allowing for clogging, the long-term infiltration capability of permeable pavements (shown red in the graph) will normally substantially exceed UK hydrological requirements (shown blue). 

Latest research

In order to better understand the effect trafficking, weathering and time have on CBPP systems, field tests have recently been undertaken by an Interpave member on three projects installed 6-, 17- and 19-years ago, respectively. To measure the permeability of these existing CBPP pavements, the trials used the American Standard ASTMC1781/C1781M method.

The research demonstrated that all the CBPP sites tested, despite receiving no specific maintenance to improve permeability, still provide infiltration rates that would cope with any rainfall event likely UK.

Demonstrative case study

One of the projects considered – Martlesham Park and Ride, Suffolk – is the subject of a video showing the trials. In this test 10 litres of water in a sealed tube created a head of about 140 millimetres – equivalent to more than a month of heavy rainfall. Here, the surface absorbed the 10 litres of water in 8 minutes and 1 second, equivalent to a rainfall intensity of 1,055mm per hour. For context, the heaviest UK rainfall event in history was 92mm per hour.

The video also includes an illuminating interview with the original project designer about long-term performance and maintenance, and also the benefits of CBPP for trees. Constructed in 2003, this large out-of-town car park receives regular daily trafficking from commuters and shoppers. With around 500 car spaces, the 13,000 m2 of concrete block permeable paving has delivered problem-free performance over 17 years.

The grit-filled joints do have moss in them but, as a porous substance itself, water passes through without problems. The site is surrounded by vegetation, with some tall trees and well-established shrubs. Maintenance has effectively been cosmetic – occasionally sweeping tree debris and vegetation from the surface after storms and leaf fall in the autumn.

Permeable paving for trees

Extensive mature trees around and within the site were simply retained as part of the scheme. The CBPP removes pollutants from water passing through, providing sustenance for the trees. The roots have continued to grow within the permeable pavement sub-base but – importantly – there have been no visible signs of block rutting or lifting, or roots coming through the surface.

As CBPP allows the same pattern of run-off transfer to the ground as natural vegetation, it allows water to reach tree and shrub roots, despite providing a hard surface above. This is endorsed by the current Code of Practice for accessibility in the external environment, BS 8300-1:2018, which states that: ‘Tree grilles should be avoided. Smooth or paved permeable surfaces should be used wherever practicable’.

Concrete block permeable paving technology will, in future, play a key role in the introduction and retention of trees, reducing air pollution and urban overheating, and increasing well-being. In addition to new permeable pavements for developments, CBPP overlays to existing, conventional road bases can be used in conjunction with raingardens or bioretention areas to collect, clean and store water for irrigation, while improving the public realm.

A full report on this research and project video – as well as more information, detailed guidance and case studies on concrete block permeable paving – are available from the Interpave website.

Banning urban pesticide use image

Banning urban pesticide use

RSPB and PAN are working on a letter from local councillors calling on the Government to introduce a national ban on urban pesticide use. Find out more below.
SIGN UP
For your free daily news bulletin
Highways jobs

Social Worker

West Northamptonshire Council
£36,734 to £39,278
We are looking for Social Workers who enjoy working in a fast-paced environment and who are passionate about promoting independence and who share the vision of ‘Home First’ and reablement, to ensure people have choice and control over their own lives Northampton
Recuriter: West Northamptonshire Council

Head of Transport Strategy & Road Safety

Warwickshire County Council
£76,594 - £84,443 per annum
We have a unique opportunity for you to shape, influence and create a better future for Warwickshire Warwickshire
Recuriter: Warwickshire County Council

Development Engineer

London Borough of Bexley
£34,476 - £39,777 per annum
The team requires someone who can inspect, measure and monitor highway works Bexley (London Borough), London (Greater)
Recuriter: London Borough of Bexley

Highway Asset and Development Manager

Bolton Council
Grade N Scp 50 £59,031 to Scp 53 £62,076, plus car allowance
To be responsible for leading, developing and delivering an effective, efficient and safe Highway Asset Management Service Bolton, Greater Manchester
Recuriter: Bolton Council

Bridge Engineer

Somerset Council
£34,834 to £39,186
We welcome applications from a diverse range of backgrounds and experiences to enrich our team. Taunton
Recuriter: Somerset Council
Linkedin Banner

Partner Content

Circular highways is a necessity not an aspiration – and it’s within our grasp

Shell is helping power the journey towards a circular paving industry with Shell Bitumen LT R, a new product for roads that uses plastics destined for landfill as part of the additives to make the bitumen.

Support from Effective Energy Group for Local Authorities to Deliver £430m Sustainable Warmth Funded Energy Efficiency Projects

Effective Energy Group is now offering its support to the 40 Local Authorities who have received a share of the £430m to deliver their projects on the ground by surveying properties and installing measures.

Pay.UK – the next step in Bacs’ evolution

Dougie Belmore explains how one of the main interfaces between you and Bacs is about to change.