Resource constraints in local planning authorities are the main cause of planning delays, according to 69% of respondents in new research from AtkinsRéalis.
The report, Planning at Pace: Creating Certainty for Investment and Delivery, found the pressure persists despite a recent influx of new planners. Other factors include statutory consultee delays (57%), inconsistent decision making (44%) and complex assessments (33%). A further 39% cited incomplete or low-quality submissions.
The delays are affecting investment, according to the report, with 62% saying planning timelines significantly influenced investment decisions or were a major determinant. The same proportion who blamed resources (69%) described decision making as slow or very slow.
The report argues that certainty matters as much as speed. It recommends expanding planning skills, standardised national templates, consultation reform and greater use of digital tools.
Chris Ball, UK & Ireland President, AtkinsRéalis, said: ‘A streamlined planning system is pivotal to the successful delivery of the UK’s infrastructure pipeline, but this research confirms that certainty is just as important as speed in building investor confidence and shifting more projects into delivery.’